330 tonnes and 22 metres long: the giant cryostat arrives at ITER

330 tonnes and 22 metres long: the giant cryostat arrives at ITER

At walking speed, the journey from Berre-l'Étang to the ITER site, a distance of 70 kilometers, would take around 16 hours. But for the cryostat, it took the Daher and Capelle teams five nights.

Measuring 22 metres long and 11 metres wide, and weighing 330 tonnes, this component is the longest and widest ever delivered to ITER. Navigating the tight curves of the 104-kilometer ITER route demanded patience and precision. Each stage of the journey required the temporary dismantling of lampposts, signs and bus stops to allow the convoy to pass.

This project, from design to delivery, was completed in just 30 months. The cryostat, manufactured by a Chinese consortium (ASIPP and SENPEC), was ready for shipment in the summer of 2025.

ITER General Manager Pietro Barabaschi attended the convoy's departure from Berre-l'Étang on September 29, alongside logistics teams from DAHER and Capelle. The special large-gauge route was perfectly negotiated, including the passage between two cliffs for which millimetric measurements had been taken.

Today, the 330-ton cryostat is stored in the former cryostat workshop, ready to be insulated before being transferred to the magnet cold test facility, already partially operational at 4 K (-269°C).

Transporting an "exceptional load" to the ITER site requires close collaboration and coordination between different entities. From left to right, during the first night of transport: operators of the Capelle transporter; representatives of DAHER, ITER's global logistics provider; Pietro Barabaschi, ITER General Manager; officers of the French Gendarmerie; and Agence Iter France, represented here by its Director, Fabrice Raynal (last in line). ©ITER
Transporting an "exceptional load" to the ITER site requires close collaboration and coordination between different entities. From left to right, during the first night of transport: operators of the Capelle transporter; representatives of DAHER, ITER's global logistics provider; Pietro Barabaschi, ITER General Manager; officers of the French Gendarmerie; and Agence Iter France, represented here by its Director, Fabrice Raynal (last in line). ©ITER
Large ITER convoys always travel at night to minimize disruption. During this five-night journey, the convoy had to cross the A51 freeway several times. ITER
Large ITER convoys always travel at night to minimize disruption. During this five-night journey, the convoy had to cross the A51 freeway several times. ITER
 The giant component reached the ITER site at 1:45 am on Saturday, October 4. It is designed to hold D-shaped toroidal field coils for testing at 4 K (minus 269°C) © ITER
The giant component reached the ITER site at 1:45 am on Saturday, October 4. It is designed to hold D-shaped toroidal field coils for testing at 4 K (minus 269°C) © ITER